Once an application is completed and submitted, SES will review the application and then post it on a secure website, accessible to "approved" Service Providers only. Assuming there is no backlog of applications this review should take no more than seven days. A project will be open for bid for seven days. During this time Service Providers will submit fixed-price bids to complete the project. The bidding system is intended to control program costs so that more Producers can have the chance to benefit from this program.
An Environmental Assessment (EA) or Nutrient Management Plan (NMP) on-farm visit must be conducted within 30 days of project award to a bidding Service Provider.
EA reports must be completed within 14 days of the on-farm visit and NMPs must be completed within 30 days of the on-farm visit.
Once a report is submitted SES will review it for quality and technical content. SES will send the report to a Producer within two week of receiving it from a Service Provider, if there are no technical or quality issues with the report.